Risk Register

Identified risks with mitigations and contingencies

7
Total Risks
3
High Impact
4
Medium Impact
7
Open
IDRiskImpactProb.Owner
R1
Unify data access delays
Category: Integration
HighMediumCircana
Mitigation:
Early engagement with Circana data team; define access requirements in Week 1
Contingency:
Use sample/synthetic data for initial POC if access delayed
R2
Web search accuracy for niche CPG brands
Category: Technical
MediumHighBounteous
Mitigation:
Curate approved source list; test with PepsiCo brands first
Contingency:
Fall back to manual context entry if search unreliable
R3
Hierarchy comparison complexity
Category: Technical
HighMediumBounteous
Mitigation:
Start with simple store count diff; iterate based on feedback
Contingency:
Reduce scope to key metrics only
R4
User adoption resistance
Category: Change
MediumLowCircana
Mitigation:
Involve CST in design; demonstrate time savings early
Contingency:
Provide hybrid mode (AI + manual override)
R5
Scope creep (Visual QC, additional clients)
Category: Scope
MediumMediumJoint
Mitigation:
Document all requests in backlog; strict change control
Contingency:
Defer to Phase 2 if timeline threatened
R6
Data security/compliance concerns
Category: Security
HighLowJoint
Mitigation:
Confirm requirements in Week 1; implement encryption and access controls
Contingency:
Run POC in isolated environment with anonymized data
R7
Holiday schedule impacts (Dec-Feb timeline)
Category: Timeline
MediumHighJoint
Mitigation:
Front-load critical work before holidays; identify key contacts
Contingency:
Adjust milestones if availability drops